The Street Project for 2023 started today on South Cherry Street!  This year's street project includes South Cherry Street, North Jackson Street (RR Tracks to East Knox Street) and North Heaton Street (RR Tracks to Lincolnway).  As part of this project, some curbing and inlets will be repaired, intersection sidewalk approaches will be reconstructed, and the road surface will be milled and overlaid with new asphalt. 

Please be aware that there will be temporary and daily road closures throughout portions of these streets as the project progresses. 

The project was awarded to Martin & Company, Oregon, Illinois. 

The City of Morrison utilized the engineering services of Willett Hofmann & Associates, Dixon, Illinois.

The project is being funded by Rebuild Illinois Funds, Motor Fuel Tax Funds, and Local 1% Sales Tax Funds at a cost of $379,381.58.  

Projected completed date is November 1, 2023.